CDM 2015 duty holders explained: client, principal designer, principal contractor and contractor duties
CDM 2015 gives every party on a construction project a defined role. Get the roles wrong and the paperwork lands with the wrong people, or with nobody. Here is who does what, in plain English, with the regulation numbers you will see in tenders and pre-qualification forms.
The six duty holders at a glance
| Duty holder | Who it is | Main duties | Key documents |
|---|---|---|---|
| Client | Anyone for whom a project is carried out | Make suitable arrangements, appoint the principal designer and principal contractor, give pre-construction information, notify HSE where required | Pre-construction information, F10 notification |
| Principal designer | A designer appointed by the client on projects with more than one contractor | Plan, manage and coordinate health and safety in the pre-construction phase | Pre-construction information, health and safety file |
| Designer | Anyone who prepares or modifies designs, or arranges for others to do so | Eliminate, reduce or control foreseeable risks through design; share information | Design risk information |
| Principal contractor | A contractor appointed by the client on projects with more than one contractor | Plan, manage and coordinate the construction phase; site induction, welfare, site rules | Construction phase plan |
| Contractor | Anyone who carries out, manages or controls construction work | Plan, manage and monitor their own work; train and supervise workers | RAMS, COSHH assessments, permits |
| Worker | Anyone working for or under a contractor | Be consulted, report risks, cooperate, follow site rules | Signed inductions and briefings |
Client (regulations 4 to 7)
The client sets the tone for the whole project. Under regulation 4 a commercial client must make suitable arrangements for managing the project, including enough time and resources, and must provide pre-construction information to every designer and contractor. Where there is, or is likely to be, more than one contractor, the client must appoint a principal designer and a principal contractor in writing (regulation 5). If the client does not appoint them, the client carries those duties itself.
The client must also make sure a construction phase plan is drawn up before the construction phase begins, and that the principal designer prepares a health and safety file.
Notification (regulation 6). A project is notifiable to HSE, using form F10, when construction work is expected to last longer than 30 working days and have more than 20 workers working at the same time at any point, or exceed 500 person-days.
Domestic clients (regulation 7). When the client is a householder having work done on their own home, their duties pass to the contractor (single-contractor projects) or the principal contractor, unless the domestic client agrees in writing that the principal designer takes them on.
Principal designer (regulations 11 and 12)
The principal designer controls the pre-construction phase: identifying, eliminating or controlling foreseeable risks, coordinating the designers, helping the client gather pre-construction information and passing relevant information to the principal contractor. The principal designer also prepares the health and safety file, and reviews and updates it as the project progresses.
Note: the Building Regulations (as amended under the Building Safety Act 2022) created a separate "principal designer" role for compliance with building regulations. One organisation can hold both roles, but they are separate appointments with different duties.
Designers (regulations 9 and 10)
Anyone who prepares or modifies a design, including architects, engineers, surveyors and contractors who design temporary works, must take into account the general principles of prevention. They eliminate foreseeable risks where reasonably practicable, reduce or control the rest, and provide information about remaining risks to the principal designer.
Principal contractor (regulations 12 and 13)
The principal contractor runs the construction phase. Before work starts it draws up the construction phase plan, then keeps it under review. It organises cooperation between contractors, makes sure every worker receives a suitable site induction, prevents unauthorised access, provides welfare facilities that meet Schedule 2 throughout the construction phase, and passes information for the health and safety file to the principal designer.
Contractors (regulation 15)
Every contractor must plan, manage and monitor the work under its control so it is carried out without risks to health and safety. In practice this means RAMS for the tasks, COSHH assessments for hazardous substances, permits where the principal contractor requires them, and workers with the right skills, knowledge, training and experience. A contractor must not start work until reasonable steps have been taken to prevent unauthorised access, and on a single-contractor project it must draw up its own construction phase plan.
Contractor paperwork in one place. Start free with CDM Creator: answer a few questions about your project and get a site-specific document ready to review and sign on screen.
Workers (regulation 14)
Workers must be consulted and engaged in matters affecting their health and safety. They must report anything they see that is likely to endanger themselves or others, cooperate with the duty holders and follow the site rules. A signed induction record and briefing record show this happened.
Who needs which document?
- Pre-construction information: client, with help from the principal designer.
- Construction phase plan: principal contractor, or the sole contractor on single-contractor projects.
- Health and safety file: principal designer, handed to the client at the end of the project. Only required where there is more than one contractor.
- RAMS, COSHH assessments, permits: each contractor for its own work.
- F10 notification: client, for notifiable projects.
Competence: skills, knowledge, experience
CDM 2015 replaced the old competence schemes with a simpler test (regulation 8): anyone appointed must have the skills, knowledge and experience, and if an organisation the organisational capability, to do the job in a way that secures health and safety. Pre-qualification schemes such as SSIP members are a common way for clients to check this, but they are not a legal requirement.
FAQ
Who are the duty holders under CDM 2015?
The client, principal designer, designers, principal contractor, contractors and workers. Each has defined duties under the Construction (Design and Management) Regulations 2015.
When must a client appoint a principal designer and principal contractor?
When there is, or is reasonably likely to be, more than one contractor working on the project. The appointments must be in writing. If the client fails to appoint them, the client takes on those duties.
Who writes the construction phase plan?
The principal contractor, before the construction phase begins. On a project with only one contractor, that contractor draws up the plan.
When is a project notifiable to HSE?
When the construction work is expected to last longer than 30 working days and have more than 20 workers working simultaneously at any point, or to exceed 500 person-days. The client notifies HSE using form F10.
Does CDM 2015 apply to domestic projects?
Yes. The domestic client’s duties pass to the contractor or principal contractor, unless the client agrees in writing that the principal designer takes them on.
This article is general guidance, not legal advice. Documents must be reviewed by a competent person and reflect the actual site and work. Sources: Construction (Design and Management) Regulations 2015 (legislation.gov.uk); HSE, Managing health and safety in construction (L153); HSE guidance on CDM 2015 roles; Building Regulations etc. (Amendment) (England) Regulations 2023.
More guides
- Construction Phase Plan under CDM 2015: what it must include
- RAMS template for UK contractors: what to include
- Permit to work in construction: types, template and when you need one
- COSHH assessment for construction: a step-by-step guide
- Excavation RAMS: lessons from the £1.15m Banstead trench collapse fines
- Free construction phase plan template (CDM 2015)
- Permit to dig: excavation permit to work and free template