Free construction phase plan template (CDM 2015)
Every construction project needs a construction phase plan before work starts. This free template follows the headings HSE recommends in its CDM 2015 guidance, with a short prompt under each one so you know what to write. Download it, fill it in for your site and keep it proportionate.
Download the template: Construction phase plan template (Word, .docx) · PDF preview. Free, no sign-up.
Who needs a construction phase plan?
Under regulation 12 of CDM 2015 the principal contractor must draw up a construction phase plan before the construction phase begins. On a project with only one contractor, that contractor writes it. The plan is required on every project, including small domestic jobs. What changes with size is the level of detail: the plan must be proportionate to the risks. For the full legal background see our guide Construction Phase Plan under CDM 2015: what it must include.
What the template covers
The template follows the structure HSE suggests in L153 (Appendix 3). Use the sections that apply to your project and delete the rest.
| Section | What to write |
|---|---|
| 1. Project description | Address, client, principal designer, principal contractor, start date and duration, scope of works, existing hazards from the pre-construction information. |
| 2. Management of the work | Site management structure and responsibilities, health and safety aims, site rules, arrangements for cooperation and coordination between contractors. |
| 3. Site induction and consultation | How every worker receives a site-specific induction, toolbox talks, how workers are consulted. |
| 4. Welfare facilities | Toilets, washing, drinking water, rest and changing areas meeting Schedule 2 of CDM 2015, available from day one. |
| 5. Emergency arrangements | Fire, first aid, rescue (including from height and confined spaces), emergency contacts, nearest A&E. |
| 6. Accident reporting | Reporting and investigating accidents and near misses; RIDDOR reporting. |
| 7. Control of significant site risks | The risks specific to your project and how they are controlled: work at height, excavations and buried services, lifting, hazardous substances, traffic and plant, demolition, asbestos, dust and noise. Reference the RAMS for each task. |
| 8. Permits to work | Activities that need a permit and who issues them. |
| 9. Health and safety file | What information contractors must pass to the principal designer for the file, and when. |
| 10. Review and sign-off | Who reviews the plan, when it is updated, signatures. |
How to fill it in: 6 practical tips
- Start from the pre-construction information. Existing services, asbestos surveys, access constraints and neighbours all belong in sections 1 and 7.
- Be specific about this site. "Work at height will be controlled" is not a plan. "Roof work from a fully boarded scaffold with double guardrails and toe boards, inspected every 7 days" is.
- Link, don't copy. Refer to the RAMS and COSHH assessments for each task rather than pasting them in full.
- Keep it proportionate. A two-week kitchen refit needs a few pages. A multi-storey new build needs much more.
- Get it to the site. The plan must be available to the people who need it, and supervisors must know what is in it.
- Review it. Update the plan when the work, the programme or the contractors change.
Prefer not to start from a blank page? Start free with CDM Creator: answer a few questions about your project and get a site-specific document ready to review and sign on screen.
Common mistakes that inspectors and clients spot
- A generic plan reused from another project, with the wrong address or hazards.
- No welfare arrangements for the first days on site.
- Significant risks listed but no controls or responsible person named.
- No emergency or rescue plan for work at height or confined spaces.
- The plan written after work has already started.
FAQ
Is a construction phase plan a legal requirement?
Yes. Regulation 12 of CDM 2015 requires a construction phase plan for every construction project before the construction phase begins, including domestic projects.
Who writes the construction phase plan?
The principal contractor. On a project with only one contractor, that contractor writes it.
How long should a construction phase plan be?
Proportionate to the size and risks of the project. A small, low-risk job may need only a few pages; complex projects need more detail.
Can I use a template for a construction phase plan?
Yes, as long as you complete it for the specific site and work. A template is a structure, not a finished plan.
Does the construction phase plan need to be sent to HSE?
No. It is kept on site and made available to those who need it. HSE inspectors may ask to see it during a visit.
This article is general guidance, not legal advice. Documents must be reviewed by a competent person and reflect the actual site and work. Sources: Construction (Design and Management) Regulations 2015, regulations 12 and 13 and Schedule 2 (legislation.gov.uk); HSE, Managing health and safety in construction (L153), Appendix 3; HSE, CDM 2015 construction phase plan guidance for small projects (CIS80).
More guides
- Construction Phase Plan under CDM 2015: what it must include
- RAMS template for UK contractors: what to include
- Permit to work in construction: types, template and when you need one
- COSHH assessment for construction: a step-by-step guide
- Excavation RAMS: lessons from the £1.15m Banstead trench collapse fines
- CDM 2015 duty holders explained: who does what
- Permit to dig: excavation permit to work and free template