Permit to dig: excavation permit to work and free template
Striking a buried cable or gas main is one of the fastest ways to injure someone on site. A permit to dig makes sure nobody breaks ground until the services have been located, marked and checked. Here is when you need one, what it must contain and a free template.
Download the template: Permit to dig template (Word, .docx). Free, no sign-up.
What is a permit to dig?
A permit to dig (also called an excavation permit or permit to break ground) is a type of permit to work. It authorises an excavation at a specific location and time, after the person issuing it has confirmed that buried services have been identified and the precautions are in place. HSE's guidance HSG47, Avoiding danger from underground services, sets out the safe system: plan the work, locate and identify the services, and use safe excavation practices.
When is a permit to dig required?
No single regulation uses the words "permit to dig", but the law requires you to prevent danger from underground services (Construction (Design and Management) Regulations 2015, regulation 25) and to have a safe system of work. Most principal contractors and utility clients therefore require a permit to dig for:
- any excavation, trench, pit or trial hole, however shallow;
- driving pins, posts, stakes or earth rods into the ground;
- breaking out hard surfaces, coring or cutting slabs;
- work near known services, or where records are missing or unreliable.
What a permit to dig must contain
| Section | What to record |
|---|---|
| Location and scope | Exact location (drawing or grid reference), dimensions and depth, method (hand dig, mechanical), dates and times. |
| Service information | Utility plans obtained and checked (electricity, gas, water, telecoms, drainage, private services), date of plans. |
| Detection | Cable avoidance tool (CAT) and signal generator used by a trained operator, date of last calibration, results. |
| Marking | Services marked on the ground, and markings still visible. |
| Trial holes | Hand-dug trial holes to confirm position and depth of services before mechanical digging. |
| Precautions | Safe digging practices near services, support of sides, edge protection, spoil away from the edge, access and egress, exclusion zones, inspections. |
| Linked documents | Reference to the excavation RAMS and any temporary works design. |
| Authorisation | Issuer signature, receiver signature and team briefing, validity period. |
| Handback | Work complete, excavation backfilled or protected, any damage to services reported. |
Permits and RAMS with e-signatures. Start free with CDM Creator: answer a few questions about your project and get a site-specific document ready to review and sign on screen.
The permit to dig process, step by step
- Plan: obtain and review service drawings before work is programmed.
- Request: the contractor requests a permit, with the excavation RAMS.
- Locate: a trained operator scans the area with a CAT and signal generator and marks services on the ground.
- Inspect and issue: the issuer checks the plans, markings and precautions, then signs the permit.
- Brief: the receiver signs and briefs the team; the permit is kept at the work area.
- Dig safely: hand-dig trial holes to expose services, re-scan as the dig deepens, and stop if an unexpected service is found.
- Hand back: the permit is closed when the excavation is complete and made safe.
Permit to dig management: who does what?
The principal contractor usually owns the permit system: it nominates authorised issuers, keeps a permit register and audits permits in use. The contractor doing the excavation provides the RAMS, competent operatives and the CAT operator. On larger sites a dedicated permit coordinator issues and closes permits each shift.
Common mistakes
- Relying on utility plans alone without scanning the area.
- CAT used in "power" mode only, missing cables that are not carrying load.
- Markings removed or faded before the dig.
- Mechanical excavators used directly over marked services.
- Permits issued for a whole job instead of a defined area and period.
See also: Excavation RAMS: lessons from the Banstead trench collapse fines.
FAQ
What is a permit to dig?
A permit to work that authorises an excavation at a specific place and time, once buried services have been located, marked and the precautions confirmed.
Is a permit to dig a legal requirement?
No regulation uses the term, but CDM 2015 (regulation 25) requires you to prevent danger from underground services and to use a safe system of work. Most principal contractors make a permit to dig mandatory.
Who can issue a permit to dig?
A competent person authorised by the principal contractor, who understands the service records, the detection results and safe digging practices.
Do I need a permit to dig for hand digging?
Usually yes. Most site rules require a permit for any ground penetration, including hand digging, driving pins and breaking out surfaces.
What guidance covers permits to dig?
HSE guidance HSG47, Avoiding danger from underground services, and HSE guidance on permit-to-work systems (HSG250).
This article is general guidance, not legal advice. Documents must be reviewed by a competent person and reflect the actual site and work. Sources: HSE, Avoiding danger from underground services (HSG47); HSE, Guidance on permit-to-work systems (HSG250); Construction (Design and Management) Regulations 2015, regulations 22 and 25 (legislation.gov.uk).
More guides
- Construction Phase Plan under CDM 2015: what it must include
- RAMS template for UK contractors: what to include
- Permit to work in construction: types, template and when you need one
- COSHH assessment for construction: a step-by-step guide
- Excavation RAMS: lessons from the £1.15m Banstead trench collapse fines
- CDM 2015 duty holders explained: who does what
- Free construction phase plan template (CDM 2015)