How to review a subcontractor's RAMS: 20-point checklist (UK, CDM 2015)
Short answer: check that the RAMS is for this job on this site, that every significant hazard in the risk assessment has a control that appears in the method statement steps, that the people and plant named are competent and inspected, and that permits, emergency and rescue arrangements and the briefing record are in place. Then decide: accept, accept with comments, or return for revision, and record why. The 20-point checklist below covers what to look at.
Why the principal contractor reviews RAMS
Under CDM 2015 regulation 13 the principal contractor must plan, manage and monitor the construction phase, organise cooperation between contractors and coordinate how they implement health and safety requirements. Each contractor, in turn, must plan, manage and monitor its own work under regulation 15. Regulation 8 also expects anyone appointing a contractor to take reasonable steps to check the contractor has the skills, knowledge and experience for the work.
The law does not name a document called "RAMS". HSE describes method statements as not required by law for most activities but an "effective and practical way to help plan, manage and monitor construction work" (HSE). In practice, reviewing the subcontractor's RAMS before work starts is how most principal contractors show they have planned and coordinated the work, and how they feed each trade's arrangements into the construction phase plan.
The 20-point RAMS review checklist
| # | Check | What good looks like |
|---|---|---|
| A. Document control | ||
| 1 | Correct project, address and scope | Site name, address and the actual package of work, not another job's details |
| 2 | Revision, date and author | Revision number, issue date, who prepared it and who approved it for the subcontractor |
| 3 | Scope boundaries | What is included and excluded, and the interfaces with other trades |
| B. Risk assessment | ||
| 4 | Task-specific hazards | Hazards for each stage of this job, including the site's own hazards (services, public, live areas) |
| 5 | Who might be harmed | Operatives, other trades, occupiers, members of the public |
| 6 | Controls follow the hierarchy | Eliminate and engineer first; PPE as the last line, not the only control |
| 7 | Residual risk is credible | Ratings change because of real controls, not because a box was ticked |
| C. Method statement | ||
| 8 | Logical sequence of work | Numbered steps in the order they happen: set-up, main task, testing, clear-up |
| 9 | Controls appear in the steps | Every control from the risk assessment is applied at the step where it is needed |
| 10 | Fits your site logistics | Access route, working hours, deliveries, storage, exclusion zones and welfare match the construction phase plan |
| 11 | Permits and hold points | Hot works, permit to dig, isolations or confined space entry identified, with who issues them |
| D. People and competence | ||
| 12 | Named supervisor | A competent person in charge on site, with contact details |
| 13 | Training and cards | Cards and tickets the task needs (e.g. CSCS, PASMA, IPAF, CPCS, SSSTS) listed, so they can be checked at induction |
| E. Plant, equipment and substances | ||
| 14 | Plant and access equipment | Named, suitable for the task, with inspection and thorough examination arrangements |
| 15 | Hazardous substances | Products listed with COSHH assessments and safety data sheets available |
| 16 | Dust, noise and vibration | Specific controls (on-tool extraction, water suppression, RPE with face-fit, exposure time limits) |
| F. Emergency, environment and sign-off | ||
| 17 | Emergency and rescue | First aid, fire, and a rescue plan for work at height, confined spaces or lifting |
| 18 | Environment and waste | Spill kit, waste segregation and removal, protection of drains and neighbours |
| 19 | PPE | Task-specific PPE on top of the site minimum |
| 20 | Briefing record | A sheet to record that operatives were briefed and signed before starting, and a trigger to re-brief if the method changes |
Accept, comment or reject: a simple decision rule
| Decision | When | Examples |
|---|---|---|
| Accept | All 20 points covered and specific to the site | Minor typos only |
| Accept with comments | Gaps that can be closed before or at the start brief without changing the method | Missing contact number, product list without SDS references, briefing sheet not attached |
| Return for revision | A significant hazard is uncontrolled, or the document is not for this job | Wrong site, no rescue plan for work at height, no sequence of work, controls in the risk assessment that never appear in the steps |
Record the decision, the reviewer and the date, and keep the comments with the RAMS. Then check on site that the work is done the way the document says. HSE points to checking that the working methods in the statement are actually put into practice.
Getting fewer RAMS sent back? If you are the subcontractor, create your first RAMS free with CDM Creator: answer questions about the job and site, and the risk assessment, method statement and briefing sheet are assembled for you to review, adapt and sign on screen. No card needed.
Red flags that usually mean a generic RAMS
- Another client's name, address or logo left in the header.
- The same risk rating on every line, or residual risk lower than any control could justify.
- "Wear appropriate PPE" as the only control for dust, noise or falls.
- No mention of the site's own hazards: live services, occupied areas, public footpaths, other trades.
- Plant listed without inspection arrangements, or no plant listed at all for work that obviously needs it.
- Fifty pages of general policy text and less than one page describing the actual sequence of work.
Tips to make reviews faster
- Send your requirements up front. Share the relevant parts of the construction phase plan, site rules, access and working hours with the tender or order, so the first RAMS is site-specific.
- Use one checklist for every trade. The same 20 points make reviews consistent and comments easier to explain.
- Comment once, clearly. Number each comment against the checklist point and say what would make it acceptable.
- Set a review time. Agree how long reviews take (for example two working days) and plan RAMS submission into the programme.
- Close the loop on site. Brief the RAMS at induction or the start-of-task brief and check the first day's work against it.
Subcontractor? Write RAMS that pass first time
Most rejections come from generic content, missing site detail and controls that never reach the sequence of work. Our guide on how much RAMS costs in the UK compares templates, consultants and software. CDM Creator's Free plan covers your first document; the Contractor plan is £39 a month and the Principal Contractor plan £99 a month (see pricing).
FAQ
Does the principal contractor have to approve subcontractor RAMS?
CDM 2015 does not use the word approve. Regulation 13 requires the principal contractor to plan, manage and monitor the construction phase and to coordinate the contractors' health and safety arrangements. Reviewing each subcontractor's RAMS before work starts is the usual way to do that and to show it was done.
Who should review a subcontractor's RAMS?
A competent person on the principal contractor's team who understands the work and the site, typically the site or project manager, often with a health and safety adviser for higher-risk work such as lifting, demolition, confined spaces or work at height.
How long should a RAMS review take?
A site-specific RAMS for routine work can usually be reviewed in under an hour against a checklist. Many principal contractors agree a turnaround such as two working days so that reviews are planned into the programme.
What are the most common reasons RAMS are rejected?
Generic content from another job, no sequence of work, controls in the risk assessment that never appear in the method statement, missing rescue arrangements for work at height or confined spaces, and no competence or plant inspection details.
Should the subcontractor's RAMS match the construction phase plan?
Yes. Site rules, access, working hours, welfare, emergency arrangements and permit systems in the RAMS should match the principal contractor's construction phase plan. Where they differ, the RAMS should be revised or the difference agreed before work starts.
This article is general guidance, not legal advice. RAMS must be prepared and reviewed by competent people and reflect the actual work and site. Sources: Construction (Design and Management) Regulations 2015, regulations 8, 12, 13 and 15 (legislation.gov.uk); HSE, Summary of duties under CDM 2015 (hse.gov.uk/construction/cdm/2015/summary.htm); HSE, Construction: what you need to do (hse.gov.uk/construction/safetytopics/admin.htm). Checked 19 November 2026.