How to write a method statement (UK construction): step by step, with an example
Short answer: a method statement explains, in the order the work happens, how a specific job will be done safely: who does it, with what equipment, which controls from the risk assessment apply at each step, and what happens if something goes wrong. Start from the risk assessment, write the sequence as numbered steps, make every step specific to the site, then get it reviewed and briefed to the people doing the work before they start.
Is a method statement required by law?
For most construction tasks, no. HSE states that method statements are "not required by law" for many construction activities, but describes them as "an effective and practical way to help plan, manage and monitor construction work" (HSE, construction administration). That planning duty is a legal one: under CDM 2015 regulation 15(2) a contractor must plan, manage and monitor the construction work it carries out. That is why almost every principal contractor asks for RAMS before you start.
Some work does need a written plan:
| Work | What the law says | Source |
|---|---|---|
| Demolition, dismantling, structural alteration | Arrangements must be recorded in writing before the work begins | CDM 2015 reg. 20; HSE |
| Work with asbestos | A suitable written plan of work detailing how the work is to be carried out | Control of Asbestos Regulations 2012, reg. 7 |
| Lifting operations | Properly planned by a competent person, appropriately supervised, carried out safely | LOLER 1998, reg. 8 |
| Work at height | Properly planned, appropriately supervised, carried out safely, including choice of equipment | Work at Height Regulations 2005, reg. 4 |
| Risk assessment (all work) | Significant findings recorded where five or more people are employed | Management Regulations 1999, reg. 3 |
For lifting and work at height the law requires planning, not a document with a particular name, but a written method statement is the usual evidence that the planning happened.
Risk assessment vs method statement
The risk assessment asks what could hurt someone and what controls do we need? The method statement answers how exactly will we do this job with those controls in place? HSE notes that a method statement can be generated from a risk assessment, so always write the risk assessment first and carry its controls into the steps.
What to include: the sections
| Section | What to write |
|---|---|
| Job and site details | Project name and address, client and principal contractor, your company, document number, revision and date |
| Scope of work | What is included and, just as important, what is not |
| People and competence | Supervisor, number of operatives, required cards and tickets (e.g. CSCS, PASMA, IPAF, CPCS) |
| Plant, equipment and materials | Access equipment, tools, lifting gear and inspection status; hazardous substances with a link to the COSHH assessment |
| Site set-up | Access route, exclusion zones, segregation from the public and other trades, welfare, storage |
| Sequence of work | Numbered steps in the order they happen, with the controls that apply to each step |
| Permits and hold points | Hot works, permit to dig, isolations, inspections before the next stage |
| PPE | Task-specific PPE on top of site minimum |
| Emergency and rescue | First aid, fire, rescue from height or confined space, nearest A&E, site contacts |
| Environmental and waste | Dust, noise, spills, waste segregation and removal |
| Briefing and sign-off | Who prepared and approved it, and a record that operatives were briefed and signed |
How to write it, step by step
- Visit the site or get the information. Access, services, other trades, working hours, client rules and the principal contractor's construction phase plan.
- Complete the risk assessment first. List the hazards for each stage and decide the controls.
- Break the job into stages in the order they will be done: set-up, preparation, main task, testing, clear-up.
- Write each step as an instruction ("Erect the tower to the manufacturer's instructions…"), naming who does it and the control that applies.
- Add the people, plant and permits the steps rely on, plus the emergency and rescue arrangements.
- Review it with the people doing the work. If they would not do it that way, change the document, not the job.
- Submit, brief and sign. Send it to the principal contractor, brief the team on site, record signatures, and revise it if the method changes.
Skip the blank page. Create your first RAMS free with CDM Creator: answer questions about the job, and the risk assessment and method statement are assembled for you to review, adapt and sign on screen. No card needed.
Worked example: replacing a first-floor window from a mobile tower
An extract from the sequence of work for a two-person window fitting team on an occupied house:
- Supervisor checks the house occupier has been told about working times and the exclusion zone. Barriers and signs are placed around the tower footprint and the drop zone below the window.
- A PASMA-trained operative erects the mobile tower on firm, level ground to the manufacturer's instructions, with guardrails and toe boards, locks the castors and records the inspection before use.
- Inside the room, dust sheets are laid and furniture moved clear. The old window is cut out from inside where possible; glass is removed first and placed in a glass stillage, never thrown down.
- The new frame is lifted to platform level by two people using the internal stairs and passed out, or by a gin wheel with a trained operative if it cannot go through the house. Nobody stands in the drop zone during the lift.
- Frame fixed, sealed and glazed; sealant and expanding foam used as per the COSHH assessment, with ventilation and gloves.
- Waste removed the same day; tower dismantled in reverse order; barriers removed last. Supervisor checks the area with the occupier before leaving.
Notice that every step says who, how and which control. That is the difference between a method statement and a list of tasks.
Mistakes that get method statements rejected
- Copied from another job: wrong address, wrong trades, wrong access arrangements.
- Steps that do not match the risk assessment, or controls in the risk assessment that never appear in the steps.
- No rescue plan for work at height or confined spaces.
- Plant and tickets not named, so the reviewer cannot check competence.
- No revision number or date, and no record of who was briefed.
- Pages of general safety text that hide the actual sequence of work.
Template or software?
A Word template is fine for occasional jobs, but you still type and tailor every document. If you price several jobs a month, software that reuses your company details, equipment and controls saves the repetition. CDM Creator's Free plan covers your first document; the Contractor plan is £39 a month (see pricing). For a comparison of the options, read How much does RAMS cost in the UK?
FAQ
Is a method statement a legal requirement in the UK?
Not in general. HSE says method statements are not required by law for most construction activities, but they are an effective and practical way to plan, manage and monitor work, which contractors must do under CDM 2015 regulation 15(2). Written arrangements are required for demolition, dismantling and structural alteration, and licensed asbestos work needs a written plan of work.
What is the difference between a risk assessment and a method statement?
The risk assessment identifies the hazards and decides the control measures. The method statement describes, step by step, how the job will actually be done with those controls in place: sequence, equipment, people, permits and emergency arrangements. Together they are usually called RAMS.
Who should write a method statement?
Someone competent who knows the job: usually the contractor's supervisor or manager, with input from the people doing the work and, where needed, a health and safety adviser. The principal contractor normally reviews it before work starts.
How long should a method statement be?
As long as the job needs and no longer. For a routine, low-risk task two to four pages is common. Higher-risk work such as lifting, work at height or excavation needs more detail on sequence, equipment and rescue.
Can I reuse the same method statement on every job?
You can reuse a well-written base document, but it must be reviewed and made specific to each site: access, other trades, services, welfare, emergency arrangements and the actual sequence of work. Generic method statements are the most common reason for rejection.
This article is general guidance, not legal advice. Method statements must be prepared and reviewed by a competent person and reflect the actual work and site. Sources: HSE, Construction: what you need to do (hse.gov.uk/construction/safetytopics/admin.htm); Construction (Design and Management) Regulations 2015, regulations 15 and 20; Control of Asbestos Regulations 2012, regulation 7; Lifting Operations and Lifting Equipment Regulations 1998, regulation 8; Work at Height Regulations 2005, regulation 4; Management of Health and Safety at Work Regulations 1999, regulation 3 (legislation.gov.uk). Checked 17 November 2026.