RAMS generator for subcontractors (UK): site-specific RAMS in 5 steps
Short answer: a RAMS generator builds your risk assessment and method statement from answers about the job, the site, your people and your plant. For a subcontractor, the output is only as good as the site detail you put in: give it the principal contractor's site rules, access, hours, permits and emergency arrangements, then review every control against your actual sequence of work before you sign and submit. Done this way, a generator saves rework compared with editing a generic Word template, and costs less than a consultant for routine jobs.
Why principal contractors ask subcontractors for site-specific RAMS
The law does not name a document called "RAMS". What it does require is that employers assess the risks of their work (Management of Health and Safety at Work Regulations 1999, regulation 3), recording the significant findings if they employ five or more people, and that every contractor plans, manages and monitors its own construction work (CDM 2015 regulation 15). The principal contractor, under regulation 13, has to coordinate all contractors' arrangements.
HSE describes method statements as not required by law for most activities but an effective and practical way to plan, manage and monitor construction work (HSE). That is why almost every principal contractor asks for RAMS before you start, and why a generic one usually comes back. Our 20-point RAMS review checklist shows what the reviewer will look for.
Template, generator or consultant: how they compare
| Option | Typical cost | Site-specific? | Best for | Watch out for |
|---|---|---|---|---|
| Free Word template | £0 | Only if you rewrite it | One-off simple jobs | Old site details left in, controls that never reach the sequence of work |
| RAMS generator (software) | Free plan to a monthly subscription | Yes, from your answers | Trades writing RAMS every week for different sites | Accepting the draft without reading it; tools with no e-signature or briefing record |
| H&S consultant | Paid per document or day rate | Yes | High-risk or unusual work (demolition, complex lifts, confined spaces) | Turnaround time; you still need to know and brief the method |
For a fuller cost breakdown see how much RAMS costs in the UK, and for a side-by-side of tools see best RAMS software for UK contractors.
5 steps to a RAMS the principal contractor accepts
- Collect the site information first. Ask for the relevant parts of the construction phase plan: site address, access route, working hours, welfare, storage, exclusion zones, permit systems, emergency and first aid arrangements, and known site hazards (live services, occupied areas, public footpaths, other trades).
- Describe your job in the generator. Scope and exclusions, the activities in order, the people (with a named supervisor), the plant and access equipment, and the substances you will use. The more specific the answers, the less you edit later.
- Check the risk assessment. Each significant hazard should have controls that follow the hierarchy (eliminate, substitute, engineer, then PPE), and residual ratings should change only because of real controls. Add COSHH assessments for products with hazardous ingredients.
- Check the method statement steps. Every control from the risk assessment must appear at the step where it is applied. Add hold points for permits such as hot works or a permit to dig, and a rescue plan for work at height, confined spaces or lifting.
- Sign, submit and brief. Add revision number, date and author, send it to the principal contractor, and keep a briefing record signed by everyone doing the work. Re-brief and revise if the method or the site changes.
Try it on your next job: create your first RAMS free with CDM Creator. Answer questions about the job and site, and the risk assessment, method statement and briefing sheet are assembled for you to review, adapt and e-sign. No card needed.
What to enter so the output is genuinely site-specific
| Input | Example | Why the reviewer cares |
|---|---|---|
| Site and scope | Address, client, "first-fix electrics, plots 12–18", exclusions | Proves the RAMS was written for this job |
| Sequence of work | Set up, isolate, install, test, clear up | Controls must be tied to real steps |
| People and competence | Supervisor name and phone, CSCS, PASMA, IPAF, 18th Edition | Checked at induction |
| Plant and equipment | Mobile tower, MEWP, 110V tools, with inspection dates | Shows equipment is suitable and inspected |
| Substances | Sealants, resins, cutting dust (silica) | Links to COSHH and dust controls |
| Site arrangements | Access gate, hours, welfare, emergency point, permits | Must match the construction phase plan |
Choosing a RAMS generator: 6 questions to ask
- Does it ask about the site, not just the task?
- Can you edit every line, and does the method statement pick up the controls automatically?
- Does it cover COSHH, permits and briefing records as well as RAMS?
- Can operatives sign electronically, and can you see who has been briefed?
- Can you reuse a RAMS for a new site and change only the site answers?
- Is there a free plan so you can test it on a real job before paying?
CDM Creator covers 100+ document types, including RAMS, COSHH assessments, construction phase plans and permits to work. The Free plan covers your first document; the Contractor plan is £39 a month and the Principal Contractor plan £99 a month (see pricing).
FAQ
What is a RAMS generator?
A RAMS generator is software that builds a risk assessment and method statement from your answers about the job, the site, the people and the plant, instead of you editing a blank template. A good one produces a draft you then review, adapt and sign; it does not replace your own knowledge of the work.
Will a principal contractor accept a RAMS made with a generator?
Principal contractors judge the content, not the tool. A generated RAMS is accepted when it is specific to the job and site, the controls in the risk assessment appear in the sequence of work, competence and plant details are included, and it matches the construction phase plan. Generic output is returned whichever tool produced it.
Is a RAMS a legal requirement for subcontractors?
The law does not name a document called RAMS. Employers must assess risks under the Management of Health and Safety at Work Regulations 1999, and record the significant findings if they employ five or more people, and contractors must plan, manage and monitor their own work under CDM 2015 regulation 15. Most principal contractors ask for RAMS before work starts as the way to show this.
How much does a RAMS generator cost?
Prices vary from free plans with limits to monthly subscriptions. CDM Creator has a Free plan for your first document, a Contractor plan at £39 a month and a Principal Contractor plan at £99 a month. Compare it with paying a consultant per document or editing Word templates yourself.
Can I use one RAMS for several sites?
You can reuse your method and controls, but each site needs its own details: address, access, working hours, welfare, emergency arrangements, permits and site-specific hazards. A generator makes this quicker because you change the site answers and keep the rest.
This article is general guidance, not legal advice. RAMS must be prepared and reviewed by competent people and reflect the actual work and site; generated documents must be checked before use. Sources: Management of Health and Safety at Work Regulations 1999, regulation 3 (legislation.gov.uk); Construction (Design and Management) Regulations 2015, regulations 13 and 15 (legislation.gov.uk); HSE, Construction: what you need to do (hse.gov.uk/construction/safetytopics/admin.htm). Checked 24 November 2026.